Scottsdale builds to the 2021 International Residential Code, 2021 International Building, Plumbing, Mechanical, Fuel Gas, and Energy codes, plus the 2020 National Electrical Code. The building and fire codes took effect January 1, 2023, with local City Council amendments layered on top of each model code.

Updated June 29, 2026 4 min read
Primary sourceCity of Scottsdale Building Code Information

Your house in Scottsdale is checked against a stack of national model codes that the City Council voted to adopt, then edited for local conditions. Knowing the exact edition matters, because a 2018 detail and a 2021 detail can call for different framing, wiring, or energy specs. This page lists the codes Scottsdale actually enforces today, when they took effect, and where the local edits live.

Which codes Scottsdale enforces

Scottsdale adopted the 2021 family of International Codes (often called I-codes) for almost everything, plus the 2020 electrical code. Here is the current list:

  • 2021 International Residential Code (IRC): one- and two-family homes and townhouses. This is the main code for a custom house.
  • 2021 International Building Code (IBC): larger and commercial structures.
  • 2021 International Energy Conservation Code (IECC): insulation, windows, duct sealing, and HVAC efficiency.
  • 2021 International Plumbing Code (IPC): water supply, drains, and fixtures.
  • 2021 International Mechanical Code (IMC): heating, cooling, and ventilation.
  • 2021 International Fuel Gas Code (IFGC): gas piping and gas appliances.
  • 2021 International Fire Code (IFC): fire safety, sprinklers, and access for firefighting.
  • 2020 National Electrical Code (NEC): all wiring and electrical work.

The IRC is the one a single-family builder lives in day to day. The City of Scottsdale is the authority having jurisdiction (AHJ) that adopts, amends, and enforces these codes, so its building officials, not the state, have the final word inside city limits.

What the city says

The city is direct about why the raw model codes do not stand alone:

Building codes are adopted and amended by City Council to account for local conditions and practices.

Scottsdale's building and fire codes took effect January 1, 2023. The energy and green code pieces, including the 2021 IRC and IECC local amendments, took effect January 7, 2023, and the green construction code amendments became mandatory July 1, 2023. Each model code has its own separate amendment document. So the rule you build to is the published 2021 edition as changed by Scottsdale's amendment PDF for that code.

When this comes into play

The edition controls real decisions from day one of design:

  • Your energy compliance path (insulation R-values, duct leakage testing, window U-factors) is set by the 2021 IECC as amended, not an older energy code. A plan drawn to a 2018 energy spec can get bounced in review.
  • Outlet spacing, arc-fault and ground-fault protection, and panel sizing follow the 2020 NEC. An electrician working off a 2017 code book may miss newer required protections.
  • Anything the model code says, a Scottsdale amendment can override. The amendment PDFs are the tie-breaker, so they get read alongside the base code.

Here is a concrete example. Say you submit a custom home plan in Scottsdale in spring 2026. The plan reviewer checks your wall insulation against the 2021 IECC as amended, your wiring against the 2020 NEC, and your framing against the 2021 IRC. If your energy sheet was copied from an older 2018 project, the duct-leakage and insulation numbers may not match, and the plan comes back with corrections before a permit issues.

If you pulled a permit before the 2023 effective dates, your project may still run under the prior edition. Edition is tied to when the permit was issued, not the calendar today.

What this means for you

Hand your designer, structural engineer, and trades one clear instruction: build to Scottsdale's 2021 I-codes and the 2020 NEC, with the city amendments applied. That single sentence prevents the most common and expensive plan-review correction, which is a sheet drawn to the wrong edition. When you compare bids, confirm each contractor is quoting current-code work, because retrofitting to code after a failed inspection costs far more than doing it right the first time.

This entry is the anchor for the rest of the Scottsdale building-codes module. From here, see Scottsdale Residential Building Permit Requirements for how these codes get checked during plan review, and Scottsdale Building Inspections for New Homes for how they get verified in the field. For the bigger picture, see the steps to building a custom home in Arizona .

Source

The adopted codes, effective dates, and amendment documents are published by the City of Scottsdale: Building Code Information on scottsdaleaz.gov . Arizona's broader adoption picture is tracked by the code authors at ICC Code Adoptions for Arizona .

This page is general information, not a code interpretation. Editions and amendments change, so confirm the current adopted code and any project-specific amendment with Scottsdale Planning and Development before you rely on a specific edition.

All City Building Codes
Desert landscape
Build With Us

Begin Your Build

Relax while we manage every detail, throughout the entire process. Tell us about your vision, and we'll be in touch to schedule a consultation.

How can we help?

Call usText us