Carefree Building Inspections for New Homes: The Sequence Through Final and CO

Carefree inspects a new home in stages, from foundation to framing to final, and each stage must pass before the work is covered up. You request inspections through the Town's Permit and License Portal, and a request must be in by 4 p.m. for the next available day. The final inspection leads to your Certificate of Occupancy.

Updated June 29, 2026 4 min read
Primary sourceTown of Carefree Building Department

In Carefree, your new home is checked at fixed milestones as it goes up, and each one has to clear before the next trade seals its work behind concrete, drywall, or stucco. The last milestone is the final inspection, and passing it is what releases your Certificate of Occupancy, the document that legally lets you move in. Below is the order, Carefree's own scheduling rule, and how the final ties to the CO.

The inspection sequence

The inspector follows the build upward and catches each stage while it is still visible. A new home runs through this order:

  1. Foundation. After the footing trench and steel are set, before any concrete is poured.
  2. Under-slab. When the plumbing, electrical, and mechanical under the floor are placed, before the slab covers them.
  3. Roof and framing. When sheathing, tie-downs, walls, fire blocking, and the rough plumbing, electrical, and mechanical are in, before any cover-up.
  4. Insulation. Before drywall.
  5. Lath. Before stucco or plaster.
  6. Final. When the home is complete and all fixtures are set, before occupancy.

The order holds because an inspector cannot approve hidden work. Suppose a framer finishes a 2,700 square foot Carefree home and the drywallers board the walls before the framing inspection is called. The inspector cannot see the wiring, plumbing rough-in, or fire blocking, so the inspection fails. The crew cuts the fresh drywall back open, re-inspects, then re-patches, costing a week and labor. The Town of Carefree is the authority having jurisdiction (AHJ) , and its Building Department sets and enforces this sequence. Because Carefree's adopted codes are the 2018 I-codes, these inspection points follow the 2018 IRC, a cycle behind newer neighbors like Cave Creek.

How scheduling and the final tie to your CO

You request inspections through the Town's online Permit and License Portal, which runs on SmartGov (twn-carefree-az.smartgovcommunity.com). Carefree sets a clear daily cutoff:

Inspection requests must be submitted by 4PM in the Permit & License Portal in order to be requested for the next available day.

The Town also notes your preferred date is not guaranteed, and you get a notice once the inspection is officially scheduled with a confirmed date and time. If you have a question about the portal, Town Hall answers at 480-488-3686. Keep your permit number ready when you request.

Nothing clears you to move in until the final passes. A passing final on a new home is what lets the Town issue the Certificate of Occupancy, the record that the house meets code and may be lived in. Carefree's portal also handles a separate Building Safety Inspection used when a business needs a Certificate of Occupancy, but for a new house the construction final is your path to the CO. Do not let any crew conceal wiring, plumbing, or framing before its inspection passes.

When this comes into play

This runs across the whole build, not only at the finish:

  • Pour days. A footing or slab cannot be poured until the foundation or under-slab inspection passes, so the 4 p.m. request deadline shapes your concrete schedule.
  • Close-in. Framing, electrical, plumbing, and mechanical are inspected before insulation and drywall. A failure here halts the cover-up.
  • Move-in. The final inspection and Certificate of Occupancy are what legally clear you to occupy. A sale or mortgage often needs the CO first.

What this means for you

Plan your trades around the 4 p.m. portal cutoff, because a request that misses it costs you a full day on the next pour or close-in. Set up your Permit and License Portal account early, request inspections there, and remember the confirmed date comes back from the Town, not from you. Never bury wiring, plumbing, or framing before it is signed off. Wait for the Certificate of Occupancy before moving family in, because occupying without it is a code violation.

This entry closes the Carefree module loop. The codes your work is inspected against are in Carefree Adopted Building Codes , and the permit that authorizes the build is covered in Carefree Residential Building Permit Requirements . For the build start to finish, see the steps to building a custom home in Arizona .

Source

The 4 p.m. inspection request cutoff and the Permit and License Portal are published by the Town of Carefree: Building Department on carefree.org . For the portal itself and permit steps, see Permits and Licenses .

This is a plain-language summary, not an official interpretation of the code. Carefree may change its cutoff, portal, or CO steps over time, so confirm today's process with the Town's Building Department before you submit a request.

All City Building Codes
Desert landscape
Build With Us

Begin Your Build

Relax while we manage every detail, throughout the entire process. Tell us about your vision, and we'll be in touch to schedule a consultation.

How can we help?

Call usText us