Fountain Hills Residential Building Permit Requirements: What You File and the Steps
A new home in the Town of Fountain Hills needs a Town building permit before construction starts. You apply through the Town's online TOPPS system with engineered site plans, two sets of construction drawings, and your parcel information. The Building Safety Division reviews the plans for code and zoning compliance, and the permit issues after fees are paid.
You cannot pour a footing or frame a wall on a new home in the Town of Fountain Hills until the Town issues a building permit. The permit is the Town's sign-off that your plans meet the adopted codes, your zoning, and your site conditions. The Building Safety Division, a work unit inside the Town's Planning and Zoning Department, handles this for any lot inside town limits. This page walks the real steps: what you gather, how you submit it, how the Town reviews it, and what it takes to get the permit in hand.
What a residential permit requires
Fountain Hills runs new-home permits through TOPPS, the Town's Online Permitting and Planning System, not over the counter. A complete residential package for a one- or two-family home comes together from these pieces:
- Two engineered site plans, drawn to scale, showing the house on the lot with setbacks (the required distance from each property line), grading, and drainage called out.
- Two sets of construction drawings, at a maximum sheet size of 24 by 36 inches and preferably at a 1/4 inch equals 1 foot scale, covering framing, electrical, plumbing, mechanical, and energy, drawn to the Town's adopted 2024 I-codes.
- A fire-sprinkler plan, because the Town's fire amendments require sprinklers in new homes, so this is not optional here.
- Your parcel number, owner and property information, and contact details.
- Sanitary District sign-off where you connect to public sewer, since the Fountain Hills Sanitary District reviews and approves the sewer connection separately from the Town.
The Town describes the division's job directly:
Through this system you can file an application, receive updates on the status of the review of the application, receive notification of application approval, and schedule inspections.
A package that is incomplete or a site plan that is not to scale gets handed back before review, which costs you days. Getting the engineered site plan and the construction set to the right scale and the right code edition the first time is the cheapest way to keep the review moving.
How review, fees, and issuance work
After you submit through TOPPS, the Building Safety Division coordinates the review of your plans for compliance with the adopted Town codes and your zoning. If corrections are required, you fix the sheets and resubmit through the same system. When the plans clear and the permit fees are paid, the permit issues, and you schedule inspections through TOPPS. Inspections run Monday through Friday, 7 a.m. to 4 p.m.
The fees are real numbers, not a mystery. For a one- and two-family home, the Town's published schedule runs roughly 73 cents per square foot for air-conditioned area and 55 cents per square foot for non-air-conditioned area, plus a landscape permit around $420 and a single-family dwelling development fee around $1,601. So a 3,000 square foot conditioned home carries a building-permit fee in the low thousands before the development and landscape fees, which is a line item you budget rather than a surprise.
Here is a real example. Suppose you submit a 2,800 square foot custom home in Fountain Hills with a site plan that shows the house too close to the front property line for your zoning district. Staff flags the setback in review. You shift the footprint or seek relief, then resubmit through TOPPS. That single correction round can add a week or two before the permit issues, which is why the site plan setbacks are worth getting right the first time.
When this comes into play
This process governs the front end of every Fountain Hills build:
- Build-on-your-lot. Your designer assembles the engineered site plan, the construction set, and the sprinkler plan, you submit through TOPPS, and the review clock runs through any correction rounds before the permit issues.
- Sewer or septic first. Many Fountain Hills lots connect to the Fountain Hills Sanitary District for sewer, which reviews your connection on its own track. A lot without sewer service may use septic, which runs through Maricopa County and the state, and the two have to line up on the same site plan before you build.
- Zoning fit. The permit confirms your home meets the Town zoning for your district, including setbacks, grading, and hillside rules. A design that overbuilds the lot or crowds a property line gets caught here, before construction.
What this means for you
Budget for the permit as a real line item, using the Town's per-square-foot rates plus the development and landscape fees, and prepare clean digital files for TOPPS. Get the engineered site plan to scale and the setbacks right the first time, because a setback problem is one of the most common reasons a residential plan gets corrected. Draw the set to Fountain Hills' current 2024 I-codes and include the required fire-sprinkler plan, so review does not stall on a wrong-code or missing-sheet correction. Line up the Fountain Hills Sanitary District sewer review in parallel, since the Town building permit alone does not approve your sewer connection. When the home passes its final inspections, the Town issues the certificate of occupancy that lets you legally move in.
This entry sits next to the codes in the Fountain Hills module. The standards your plans are checked against are listed in Fountain Hills Adopted Building Codes . If your lot is on septic or a private well, the water and wastewater side follows the county and state, covered in Maricopa County Septic and Well Requirements for a New Home . For the full picture of a custom build, see the steps to building a custom home in Arizona .
Source
The division's role, the TOPPS online system, and the inspection hours are published by the Town of Fountain Hills: Building Safety on fountainhillsaz.gov . The application forms, checklists, and fees are at Permits & Applications and Building Permit Forms & Checklists . The separate sewer review is handled by the Fountain Hills Sanitary District .
This page is general information, not a substitute for the Town's current applications and checklists. Submittal items, fees, and timelines change, so confirm the live requirements with the Town of Fountain Hills Building Safety Division before you file.