A.R.S. 33-1006: Releasing a Paid-Off Mechanics Lien in Arizona

Arizona A.R.S. 33-1006 gives a lien claimant twenty days to record a release once a mechanics lien is paid off. If they miss that window, they owe you one thousand dollars plus any actual damages the unreleased lien causes. This is the law that clears a satisfied lien off your new home's title.

Updated July 23, 2026 3 min read
Primary sourceA.R.S. 33-1006 Release of mechanic's and materialman's liens; liability

A paid mechanics lien does not fall off your home's title on its own. Someone has to record a release. Arizona law puts that job on the lien claimant, sets a hard deadline, and adds a penalty if they drag their feet. That matters most when a sub or supplier has already been paid in full and still has a lien sitting against your new house.

What the statute requires

Once a mechanics lien is satisfied, meaning it has been paid or otherwise resolved, the claimant has a short window to clear it:

When any lien established by the provisions of this article has been satisfied, the lienholder shall, within twenty days after satisfaction, issue a release of the lien.

Twenty days is the whole clock. The same duty applies when an owner-occupant sends a written request about a lien that should never have attached to their home. That ties directly to the owner-occupied dwelling exemption. The release also has to meet Arizona's standard recording-document format under A.R.S. 11-480, or the county recorder can reject it.

The penalty for sitting on a release

A claimant who ignores the twenty-day deadline owes you money:

Failure to grant such a release shall subject the lienholder or person to liability in the amount of one thousand dollars and also to liability for actual damages.

So a claimant who was paid and still refuses to release owes a flat one thousand dollars plus whatever the lingering lien actually costs you. On a new home, that damage number can climb fast. An open lien can block a closing, freeze a construction-to-permanent loan conversion, or force a rate-lock extension.

What it means for your build

Suppose your framing subcontractor recorded a mechanics lien during the build, and you clear it with a forty thousand dollar payment. Once that payment lands and the lien is satisfied, the sub has twenty days to record the release. Now put yourself fifteen days from closing on your permanent loan. Do the subtraction. The sub's twenty-day window runs five days past your closing date, so a claimant who takes every day the statute allows is still inside the law while the lien sits on your title the morning you sign. If the sub lets the release slide past day twenty, the statute makes them liable for the flat thousand dollars. On top of that comes your actual damage, such as an extension fee on your rate lock.

Do not rely on the deadline alone. Get a signed release or lien waiver at the moment of each payment. Then confirm the release is actually recorded at the county recorder, not just handed to you.

How this connects to the rest of the lien process

Section 33-1006 is the exit door of Arizona's mechanics lien system. It closes out the chain that starts with the right to a lien and recording the lien. It works alongside the lien waivers you collect at each draw, which keep liens from surviving payment in the first place. If a lien is already clouding your title, walk through how to remove a mechanics lien from your Arizona home. The exact wording, including the twenty-day clock and the recording standard it points to, is in A.R.S. 33-1006.

Keep exploring

All Arizona Building Law
Desert landscape
Build With Us

Begin Your Build

Relax while we manage every detail, throughout the entire process. Tell us about your vision, and we'll be in touch to schedule a consultation.

How can we help?

Call usText us